Hwy #37 through Gull Lake: 1.3 km of road reconstruction including new concrete curbs and gutters and an asphalt surface on Highway No. 37 within the town limits of Gull Lake. The limits of the project are from 0.2 km south of its junction with Grey Street to 0.1 km north of 7th Street.
• Detours will be in effect for non-local traffic using Green Terminal Road – signage will be posted on Hwy #1 (east & west) and Hwy #37 (north & south)
• Local traffic will have access to the Town of Gull Lake at all times
• Two consecutive blocks will be closed at a time with local traffic being detoured to adjacent streets during closures with at least one back-alley access
• Construction will begin May 7th on Rutland Avenue starting at Third Street and working North to Fifth Street (first two block section)
We will post regular updates as construction progresses. Any questions can be forwarded to the Town Office at 306-672-3361